"Where in all of Hawaiʻi do we have a place for hula? Where?" Kumu Hula Hōkūlani Holt asked at the site blessing in April 2025, as Hawaiʻi Public Radio reported. "Nowhere. What a shock that was. We have football fields, soccer fields, skate parks, pickleball, but where is hula?" The concrete going up at the corner of Church and Vineyard streets is the County of Maui's answer to her. It's the Hālau of ʻŌiwi Art, which HPR described as Hawaiʻi's first government-funded center for hula and Hawaiian arts.
Anyone who drives through Wailuku town has watched the slabs go up. The more useful story is in the budget. Cost cuts after the 2023 bid stripped out the building's decorative finishes. The $4 million the County Council added this year went almost entirely to equipment: a commercial kitchen, sound and video systems, acoustic treatment for the second-floor hall, and solar on the roof. That money is what will let kumu, kūpuna and families actually use the place.
A hall laid out around what happens inside it
Maui Now's May 2026 coverage describes a two-story building of about 47,000 square feet. It's designed to hurricane standards and is now going vertical. Here is what's planned inside:
- Ground floor: incubator retail space
- Second floor: studios and practitioner space
- A large gathering and performance hall
- A commercial kitchen
- A courtyard connecting the spaces
HPR reported that it will host Kaunoa Senior Services classes and that the County plans to use it as a disaster shelter and a resiliency and recovery center. Maui Now added that it will act as a joint information center during emergencies. At the April 2025 blessing, Mayor Richard Bissen said the center "will include spaces, both indoors and outdoors, for performances and gatherings to serve our community."
The building was shaped from the start by people who teach hula. HPR reported that it grew out of a collaboration among Maui hula hālau of different traditions, with Holt leading the steering committee. County ʻŌiwi Resources Director and Kumu Hula Kaponoʻai Molitau gave the blessing over the site before contractor F&H Construction broke ground.
Why a County builds a hula hall the way it builds a ballfield
The lot has its own history. It was meant for the Wailuku Civic Center. During the May budget hearing, Council Member Keani Rawlins-Fernandez traced the hālau back to a 2019 Council resolution supporting the Huamakahikina Declaration. After the civic center project lost its funding, the hālau idea took its place.
She described a bigger plan, as Maui Now reported:
"This wasn't meant to be the only one. It was meant to have one in every district."
She compared those future hālau to the baseball fields, swimming pools and gyms the County already builds in each district.
Holt made the same comparison to playing fields. That framing explains the budget fight. A ballfield isn't finished until it has lights and bleachers, and a hula hall isn't finished until it has sound, acoustics and a kitchen to feed a crowd.
What the 2023 bid took out
Council members heard in May that the project went out to bid in fall 2023. The low bid was $52.7 million, about $6.2 million over budget. Instead of canceling, the County went ahead with construction and worked with the contractor to bring the cost back down.
The cuts landed mostly on looks. Maui Now listed them: the walls changed from cast-in-place concrete to mostly precast tilt-up panels, the roofing material changed, and the design dropped high clerestory windows, exposed wood beams, stone masonry veneer and stamped concrete in the courtyard. County civil engineer Dan Shupack told the committee the switch to tilt-up walls makes no difference to structural quality, only to cost and installation time.
Council Member Tom Cook is a contractor. He suggested restoring features that are hard to change after the building is finished, like the original standing-seam metal roof. He also suggested community fundraising to pay for finish items like the stamped concrete.
What the $4 million put back
Some items had been bid as optional add-ons that the original contract couldn't afford. Bills 70 and 80 of 2026 asked for $4 million in bond funding to restore them. When Council Member Nohelani Uʻu-Hodgins asked for a breakdown, Shupack gave these rough figures:
| Restored item | Approximate cost |
|---|---|
| Audio-visual systems | $1.04 million |
| Professional services contract extensions | $854,000 |
| Commercial kitchen equipment | $770,000 |
| Telecom, data and security infrastructure | $652,000 |
| Rooftop photovoltaic system | $532,000 |
| Acoustic treatments | $194,000 |
The two biggest building items, sound and video plus the kitchen, are what turn a large empty room into a place for a hōʻike or a pāʻina. The $194,000 for acoustics is aimed at the second-floor event space, according to Maui Now. The solar matters too. Officials said the photovoltaic system would help the building reach LEED Gold certification, which they called a first for a county facility.
With the add-backs, contract extensions and allowances for rising costs, the estimated total is about $50.5 million. The original budget was $46.5 million, including $11 million in congressional direct spending. On the agenda for the Council's June 19 meeting, the $4 million appropriation for the Hālau of ʻŌiwi Art appears as Bill 70, CD1, listed as Ordinance 6005. The companion bond bill, Bill 80, is listed as Ordinance 6006.
A bridge to the garage you already park in
Most of Wailuku already knows the building next door. The Hālau sits beside the Wailuku Parking Garage, and crews have built the forms for a pedestrian bridge between the two, according to the October 2 construction update on Wailuku Live.
That garage has become part of First Friday. For the November 6 event, themed "Wailuku Gives," Maui Now reported that the garage hosted dance and DJ programming while Nevah Too Late played on Market Street. Free garage parking opened at 6 p.m., with the entrance on Church Street between Vineyard and Main. Once the bridge opens, the same garage that serves Market Street on First Friday will also connect straight into a performance hall. The next First Friday is listed for December 4. If Market Street is your monthly routine, our Wailuku summer guide covers the rest of the block.
Where construction stands this month
The weekly updates on Wailuku Live give a clear timeline:
- April 28, 2025: Construction begins.
- Early October 2026: Crews backfill and compact Level 1 areas labeled Retail 2, Retail 5 and Workshop 2. They also pour concrete for the Level 2 deck and build forms for the garage bridge.
- October 30, 2026: Crews finish pouring and finishing the Level 2 concrete slab for the future studio area.
- April 19, 2027: Scheduled construction completion, subject to change.
- Fall 2027: The grand opening timeframe officials gave the Council in May.
Neighbors near Vineyard and North Church should expect normal commercial construction noise until then. Questions go to F&H Construction Superintendent Terry at 808-495-7952. For a look between drive-bys, Wailuku Live runs a live video feed of the site at wailukulive.com/hoa.
If you'd like to talk through how projects like this shape life in Wailuku town, Matt Talbot would be glad to share what he's following on our Wailuku neighborhood page or over coffee near Market Street. Start the conversation here.